POTENTIAL FACILITY OPTIONS


Introduction

The following information has been developed and/or reviewed by our PRIDE committee in the preparation of potential options:

Some of the major preferences identified by the community during the first community meeting were:


Elementary School Level

The results of the first community meeting indicates that the participants of the workshop prefer the following program changes:

The following chart reflects the projected enrollments for the next ten years for both a K - 5 and a K - 6 grouping. Please note that these projections suggest a future enrollment of 3,375 for K - 5 and 3,965 for K - 6.

MOST LIKELY ELEMENTARY PROJECTED ENROLLMENTS

Year K-5 K-6
1995 3036 3555
1996 3017 3603
1997 3070 3608
1998 3166 3655
1999 3277 3766
2000 3329 3879
2001 3324 3929
2002 3364 3927
2003 3364 3965
2004 3375 3964

In addition to above projections, pre-kindergarten mandated programs could generate an additional 100 students or more.


Conditions of Existing Elementary Buildings

The school system needs space to accommodate approximately 3,375 students at the K-5 level or 3,965 students at the K-6 level. The needed capacity with a 25:1 studentIteacher ratio would be 135 rooms for K-5 or 160 rooms for K-6. There are 127 permanent classrooms now available.

The qualitative evaluation of current school facilities suggest:


Middle School Level

The results of the first community meeting indicates that the participants of the workshop prefer the following program changes:

The following chart reflects the projected enrollments for 6 - 8. 7 - 8, and 7 - 9 grade groupings.

MOST LIKELY MIDDLE OR JUNIOR HIGH PROJECTED ENROLLMENTS

Year6 - 87 - 87 - 9
1995164611271675
1996169111051666
1997168211441713
1998165211631702
1999155110621670
2000156210121570
2001168110761584
2002175911961703
2003181112091780
2004179412051833


Condition of Existing Junior High Schools

The qualitative evaluation of the existing school facilities suggest:


High School Level

The results of the first community meeting indicated that the participants of the workshop prefer the following: The following chart reflects the projected enrollments for 9 - 12 and 10 - 12 grade groupings.

MOST LIKELY HIGH SCHOOL PROJECTED ENROLLMENTS*

Year9-1210-12
199520201472
199620451484
199721141545
199820851546
199921441536
200021411583
200120791571
200220431536
200320171446
200420931465

Excludes anticipated Career Center students.


Condition of Existing High School

The qualitative evaluation of the existing school facilities suggest:


OVERALL DISTRICT OPTIONS

The options outlined below have been developed to provide comparisons for adequate educational facilities through the decade of the 1990s and into the 21st century.

The costs of the various options are based on rough estimates. More precise cost estimates should be made once the educational specifications are developed by local users and costs are made by estimators. The presented dollar amounts should be viewed as approximations for strategic planning purposes.